Project Insights
-
Client
Hyde
- Contract Value £5,400,000.00
- Duration 14 Months
- Address Bermondsey Spa
- Development The removal and replacement ACM external cladding and Internal Fire Stopping.
Description
When the testing was first announced by the MHCLG, our existing clients selected Martin Arnold and we were instructed to visit and organise testing of around 100 blocks within London and the South East. This commission involved attending the sites and identifying potential ACM materials that would require testing. We coordinated the removal of the samples and managed the sample issue to the BRE. Following this we were instructed to design and manage the replacement of the defective ACM cladding along with some further issues found internally with the fire stopping as highlighted by the Type 4 FRA.
We are currently Contract Administrator on a number of ACM replacement schemes. As part of this commission we provided the scheme with an enhanced Quality Control (Clerk of Works) resource on site everyday to record, advise and manage the removal and replacement process.
USP
Works were successfully completed earlier this year. The project was unique as it was one of the first to have completed following the advice given by the MHCLG to remove ACM type cladding from Buildings over 18m. This was the project where we developed the Gridline System for accurate recording.